A rescheduling heuristic for the single machine total tardiness problem

JC Nyirenda

Abstract


In this paper, we propose a rescheduling heuristic for scheduling N jobs on a single machine in order to minimise total tardiness. The heuristic is of the interchange type and constructs a schedule from the modified due date (MDD) schedule. Unlike most interchange heuristics that consider interchanges involving only two jobs at a time, the newly proposed heuristic uses interchanges that may involve more than two jobs at any one time. Experimental results show that the heuristic is effective at reducing total tardiness producing schedules that either similar or better than those produced by the MDD alone. Furthermore, when applied to some test problems the heuristic found optimal schedules to all of them.

Full Text:

PDF


DOI: https://doi.org/10.5784/22-1-34

Refbacks

  • There are currently no refbacks.





ISSN 2224-0004 (online); ISSN 0259-191X (print)

Powered by OJS and hosted by Stellenbosch University Library and Information Service since 2011.


Disclaimer:

This journal is hosted by the SU LIS on request of the journal owner/editor. The SU LIS takes no responsibility for the content published within this journal, and disclaim all liability arising out of the use of or inability to use the information contained herein. We assume no responsibility, and shall not be liable for any breaches of agreement with other publishers/hosts.

SUNJournals Help